Fault Codes:Case General E0377
What is CaseGeneral Fault Code E0377?
CaseGeneral Fault Code E0377 indicates a fault in the Fuel Pump Power Cut-Off Relay circuit — specifically, the ECM has detected an abnormal electrical condition in the relay that controls power delivery to the fuel pump.
The fuel pump power cut-off relay is a critical component in the fuel supply system. It acts as an electronically controlled switch that the ECM energizes to allow fuel flow during normal operation and de-energizes to cut fuel in emergency shutdown scenarios.
When the ECM cannot confirm proper relay operation — either because it detects incorrect voltage feedback, an open circuit, or a short — it logs E0377 and may initiate protective actions to prevent engine damage or uncontrolled fuel delivery.
Common Symptoms
- Illuminated warning light or fault indicator on the instrument cluster
- Engine fails to crank or start, with no fuel pump prime cycle audible
- Unexpected engine shutdown or inability to restart after a normal stop
- Engine enters derate mode, limiting power and hydraulic performance
- Intermittent stalling under load, particularly in older machines with harness wear
Potential Causes
- Failed or stuck fuel pump power cut-off relay — internal contacts burnt or welded from age and heat cycling
- Open or short circuit in the relay control wiring between the ECM and the relay coil terminal
- Corroded or loose connector pins at the relay socket or the ECM harness connector — extremely common on used and high-hour machines
- Harness chafing against the firewall, engine mounts, or frame rails — a known wear point on older CaseGeneral excavators where the main engine harness passes near the battery tray
- ECM power supply or ground integrity issues causing false relay fault detection
- Blown fuse in the relay control circuit, often caused by a prior intermittent short
How to Troubleshoot and Fix Code E0377
Step 1 — Read and Document Active Faults
Connect a CaseGeneral-compatible diagnostic tool (such as the Case SiteWatch service tool or a compatible J1939 scanner) and record all active and stored fault codes. Note the freeze-frame data to understand the operating conditions when E0377 was triggered. Clear codes only after documenting.
Step 2 — Inspect the Relay and Fuse First
Locate the fuel pump power cut-off relay in the main fuse and relay box. Remove the relay and test it on the bench: apply 12V across the coil terminals and confirm audible click and continuity across the switching terminals with a multimeter. Check the associated fuse for continuity. On used excavators, inspect the relay socket for burnt plastic, melted terminals, or green corrosion — replace the socket if contaminated, not just the relay.
Step 3 — Check the Relay Control Circuit Wiring
With the relay removed and the ignition on, use your multimeter to check for battery voltage at the relay supply terminal. Then backprobe the ECM relay control output wire: the ECM should pull this circuit to ground when commanding the relay on. Resistance on this wire should read below 2 ohms from pin to pin. Any reading above that indicates a damaged conductor or corroded connector.
Step 4 — Inspect the Harness for Wear and Corrosion
On used excavators, this step is essential before ordering parts. Trace the entire relay wiring harness from the relay box back to the ECM connector. Pay close attention to areas where the harness passes through bulkheads, over frame edges, or near the battery box — these are the highest-friction rub points on CaseGeneral machines. Look for cracked insulation, bare copper, or pinched sections. Inspect every connector in the circuit for pushed-back pins, moisture intrusion, or white/green oxidation. Apply dielectric grease to cleaned connectors before reassembly.
Step 5 — Verify ECM Ground and Supply Integrity
A weak ECM ground can cause false relay feedback faults. Measure voltage drop between the ECM ground bolt and the negative battery terminal with the engine running — anything above 0.1V indicates a poor ground path. Clean and re-torque all ECM ground connections. Verify battery voltage at the ECM main supply connector is within 11.5–14.5V during cranking.
Step 6 — Retest and Confirm Repair
After completing repairs, reconnect all components, clear the fault codes with the diagnostic tool, and perform a full ignition cycle. Confirm the fuel pump primes normally on key-on and that E0377 does not return after a loaded test cycle. If the fault persists after relay, harness, and connector repairs have been verified, suspect internal ECM relay driver failure and consult a CaseGeneral dealer for ECM testing.
Disclaimer: This guide is provided for informational and diagnostic reference purposes only. Fuel system and ECM-related repairs should be performed by a qualified heavy equipment mechanic with appropriate training and tools. Always follow manufacturer safety procedures when working on diesel fuel systems. FairTrade Machinery assumes no liability for repairs performed based on this content.
Fault Description:
Fuel pump power cut-off relay
FairTradeMachinery
You Design the Vision. We Handle the Hard Parts.
Helping Global Buyers Access Better-Value Machinery and After-Sales Solutions.
As China's Leading Global Used Machinery Exchange Platform, we sits at the intersection of IoT technology and B2B commerce. That means real-time inventory data, verified seller profiles, and a transaction process designed for cross-border buyers who can't always inspect machines in person. Our users in China have exceeded 1.5 millions meaning we have the first source of excavator owners and the equivalent number of machines. This means we can cover all the popular models and even specific needs, no matter of the status.







FAQs
WhatsApp